Project Status Report April 2006

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.

Project Status:

PROJECT NO. CIP 02-104 BAYVIEW POST-UNDERGROUNDING STREET IMPROVEMENTS

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 12/09/05
DESIGN & ENGINEERING (PS&E)07/06
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTION3RD QTR FY 06-07 EST.
END CONSTRUCTIONTBD

PROJECT NO. CIP 02-106 BEACH DRIVE POST-UNDERGROUNDING STREET IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03-10-05
DESIGN & ENGINEERING (PS&E)07/06
TO PW COMMISSION FOR REVIEW07/06
TO COUNCIL FOR APPROVAL TO ADVERTISETBD UPON COMPLETION OF UUD
BID OPENINGTBD UPON COMPLETION OF UUD
TO COUNCIL FOR AWARDTBD UPON COMPLETION OF UUD
BEGIN CONSTRUCTION2ND QTR FY 06-07 (EST)
END CONSTRUCTIONTBD UPON COMPLETION OF UUD

PROJECT NO. CIP 05-109 CONCRETE ROAD RECONSTRUCTION - VARIOUS LOCATIONS

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)COMPLETED 04/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARD06/06
BEGIN CONSTRUCTION07/06
END CONSTRUCTION10/06

PROJECT NO. CIP 05-110 SLURRY/CRACK SEALING AT VARIOUS LOCATIONS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERING05/06
DESIGN & ENGINEERING (PS&E)07/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING08/06
TO COUNCIL FOR AWARD08/06
BEGIN CONSTRUCTION09/06
END CONSTRUCTION09/06

PROJECT NO. CIP 04-112 STREET IMPROVEMENTS - SLURRY SEAL AT VARIOUS LOCATIONS

DESCRIPTIONSTATUS

REVISED

PRELIMINARY ENGINEERINGCOMPLETED 03/04/05
DESIGN & ENGINEERING (PS&E)07/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING08/06
TO COUNCIL FOR AWARD08/06
BEGIN CONSTRUCTION09/06
END CONSTRUCTION09/06

PROJECT NO. CIP 04-116 STREET IMPROVEMENTS - PIER AVE., HERMOSA AVE. TO PCH

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERING06/06
DESIGN & ENGINEERING (PS&E)07/06
TO PW COMMISSION FOR REVIEW09/06
TO COUNCIL FOR APPROVAL TO ADVERTISE10/06
BID OPENING11/06
TO COUNCIL FOR AWARD12/06
BEGIN CONSTRUCTION01/07
END CONSTRUCTION06/07

PROJECT NO. CIP 04-117 STREET IMPROVEMENTS - MANHATTAN AVE. 1ST ST. TO CITY LIMITS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)05/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARD06/06
BEGIN CONSTRUCTION07/06
END CONSTRUCTION10/06

PROJECT NO. CIP 04-118 STREET IMPROVEMENTS - STRAND BIKEWAY LIGHT FIXTURE REPLACEMENT

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)N/A
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 12/01/05
TO COUNCIL FOR AWARDCOMPLETED 01/10/06
BEGIN CONSTRUCTION05/06
END CONSTRUCTION06/06

PROJECT NO. CIP 05-119 STREET IMPROVEMENTS - HERMOSA AVE., LONGFELLOW AVE.

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)TBD
TO PW COMMISSION FOR REVIEWTBD
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARD2ND QTR FY 06-07
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 05-120 STREET IMPROVEMENTS - VARIOUS LOCATIONS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 04/06
DESIGN & ENGINEERING (PS&E)05/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 05/15/06
TO COUNCIL FOR AWARD06/06
BEGIN CONSTRUCTION07/06
END CONSTRUCTION10/06

PROJECT NO. CIP 05-121 STREET IMPROVEMENTS - AVIATION BLVD. TREE PROJECT

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 8/31/05
DESIGN & ENGINEERING (PS&E)06/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING07/06
TO COUNCIL FOR AWARD07/06
BEGIN CONSTRUCTION08/06
END CONSTRUCTION09/06

PROJECT NO. CIP 00-413 SEWER IMPROVEMENTS - TARGET AREAS 2 THRU 4

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 07/15/05
DESIGN & ENGINEERING (PS&E)06/06
TO PW COMMISSION FOR REVIEW06/06
TO COUNCIL FOR APPROVAL TO ADVERTISE07/06
BID OPENING07/06
TO COUNCIL FOR AWARD07/06
BEGIN CONSTRUCTION08/06
END CONSTRUCTION10/06

PROJECT NO. CIP 03-418 UPGRADE OF SEWER PUMP STATIONS

DESCRIPTIONSTATUS
 
PRELIMINARY ENGINEERINGCOMPLETED 04/28/05
DESIGN & ENGINEERING (PS&E)COMPLETED 12/31/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 07/26/05
BID OPENINGCOMPLETED 04/27/06
TO COUNCIL FOR AWARD05/06
BEGIN CONSTRUCTION06/06
END CONSTRUCTION09/06

PROJECT NO. CIP 04-534 PARK IMPROVEMENTS - HOMAYOUN BEHBOODI, PROJECT ENGINEER

DESCRIPTIONSTATUS-REVISED
E. RODAWAY PARK
PRELIMINARY ENGINEERINGCOMPLETED 2/06
DESIGN & ENGINEERING (PS&E)TBD
TO PW COMMISSION FOR REVIEWTBD
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 04-535 CLARK FIELD IMPROVEMENTS - KEN REAMEY, PROJECT ENGINEER

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGCOMPLETED 04/13/06
DESIGN & ENGINEERING (PS&E)05/06
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING06/06
TO COUNCIL FOR AWARD06/06
BEGIN CONSTRUCTION07/06
END CONSTRUCTION08/06

PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION - PHASE 2 - HOMAYOUN BEHBOODI , PROJECT ENGINEER

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGCOMPLETED 11/01/05
DESIGN & ENGINEERING (PS&E)COMPLETED 11/08/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES PHASES 3 & 4 - HOMAYOUN BEHBOODI, PROJECT ENGINEER

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 9/30/04
DESIGN & ENGINEERING (PS&E)COMPLETED 7/10/05
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 02/09/06
TO COUNCIL FOR AWARDCOMPLETED 3/28/06
BEGIN CONSTRUCTION05/06
END CONSTRUCTION07/06

PROJECT NO. CIP 99-631 BEACH RESTROOMS - REHABILITATION

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGCOMPLETED 03/31/06
DESIGN & ENGINEERING (PS&E)06/06
TO PW COMMISSION FOR REVIEW07/06
TO COUNCIL FOR APPROVAL TO ADVERTISETBD
BID OPENINGTBD
TO COUNCIL FOR AWARDTBD
BEGIN CONSTRUCTIONTBD
END CONSTRUCTIONTBD

* TBD - TO BE DETERMINED