Project Status:
PROJECT NO. CIP 02-104 BAYVIEW POST-UNDERGROUNDING STREET IMPROVEMENTS FRANK SENTENO, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| REVISED |
| PRELIMINARY ENGINEERING | 11/05 |
| DESIGN & ENGINEERING (PS&E) | 02/06 |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 02-106 BEACH DRIVE POST-UNDERGROUNDING STREET IMPROVEMENTS FRANK SENTENO, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| REVISED |
| PRELIMINARY ENGINEERING | COMPLETED 03-10-05 |
| DESIGN & ENGINEERING (PS&E) | 11/05 |
| TO PW COMMISSION FOR REVIEW | 11/05 |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD UPON COMPLETION OF UUD |
| BID OPENING | TBD UPON COMPLETION OF UUD |
| TO COUNCIL FOR AWARD | TBD UPON COMPLETION OF UUD |
| BEGIN CONSTRUCTION | TBD UPON COMPLETION OF UUD |
| END CONSTRUCTION | TBD UPON COMPLETION OF UUD |
PROJECT NO. CIP 05-109 CONCRETE ROAD RECONSTRUCTION VARIOUS LOCATIONS TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| |
| PRELIMINARY ENGINEERING | 1/06 |
| DESIGN & ENGINEERING (PS&E) | 2/06 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
| BID OPENING | 4/06 |
| TO COUNCIL FOR AWARD | 4/06 |
| BEGIN CONSTRUCTION | 5/06 |
| END CONSTRUCTION | 6/06 |
PROJECT NO. CIP 05-110 SLURRY/CRACK SEALING AT VARIOUS LOCATIONS TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 04-112 STREET IMPROVEMENTS SLURRY SEAL AT VARIOUS LOCATIONS TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
|
REVISED |
| PRELIMINARY ENGINEERING | COMPLETED 03-04-05 |
| DESIGN & ENGINEERING (PS&E) | 02/06 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
| BID OPENING | 03/06 |
| TO COUNCIL FOR AWARD | 04/06 |
| BEGIN CONSTRUCTION | 05/06 |
| END CONSTRUCTION | 06/06 |
PROJECT NO. CIP 04-113 STREET IMPROVEMENTS CONCRETE ROAD RECONSTRUCTION AT VARIOUS LOCATIONS TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
|
REVISED |
| PRELIMINARY ENGINEERING | COMPLETED 03-04-05 |
| DESIGN & ENGINEERING (PS&E) | COMPLETED 04-28-05 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A |
| BID OPENING | COMPLETED 06/16/05 |
| TO COUNCIL FOR AWARD | COMPLETED 06/28/05 |
| BEGIN CONSTRUCTION | COMPLETED 08/29/05 |
| END CONSTRUCTION | 09/26/05 ONLY PUNCHLIST ITEMS REMAIN |
PROJECT NO. CIP 04-115 STREET IMPROVEMENTS 20TH ST. FROM VALLEY DR. TO POWER ST. TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | COMPLETED 08/16/04 |
| DESIGN & ENGINEERING (PS&E) | COMPLETED 01/20/05 |
| TO PW COMMISSION FOR REVIEW | COMPLETED 12/05/04 |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 02/08/05 |
| BID OPENING | COMPLETED 03/10/05 |
| TO COUNCIL FOR AWARD | COMPLETED 03/22/05 |
| BEGIN CONSTRUCTION | COMPLETED 06/21/05 |
| END CONSTRUCTION | COMPLETED 08/16/05 |
PROJECT NO. CIP 04-116 STREET IMPROVEMENTS PIER AVE., HERMOSA AVE. TO PCH FRANK SENTENO, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| REVISED |
| PRELIMINARY ENGINEERING | 11/05 |
| DESIGN & ENGINEERING (PS&E) | 07/06 |
| TO PW COMMISSION FOR REVIEW | 09/06 |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 10/06 |
| BID OPENING | 11/06 |
| TO COUNCIL FOR AWARD | 12/06 |
| BEGIN CONSTRUCTION | 01/07 |
| END CONSTRUCTION | 06/07 |
PROJECT NO. CIP 04-117 STREET IMPROVEMENTS MANHATTAN AVE. 1ST ST. TO CITY LIMITS TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| REVISED |
| PRELIMINARY ENGINEERING | COMPLETED 10/26/04 |
| DESIGN & ENGINEERING (PS&E) | 12/05 |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 04-118 STREET IMPROVEMENTS STRAND BIKEWAY LIGHT FIXTURE REPLACEMENT HOMAYOUN BEHBOODI, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 05-119 STREET IMPROVEMENTS HERMOSA AVE., 26TH 35TH STS.; LONGFELLOW AVE., MANHATTAN TO INGLESIDE FRANK SENTENO, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 05-120 STREET IMPROVEMENTS VARIOUS LOCATIONS, TRISTAN MALABANAN PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | 11/05 |
| DESIGN & ENGINEERING (PS&E) | 12/05 |
| TO PW COMMISSION FOR REVIEW | 12/05 |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 05-121 STREET IMPROVEMENTS AVIATION BLVD. TREE PROJECT RICK MORGAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
|
REVISED |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 99-409* MANHOLE REPAIR/RECONSTRUCTION TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
|
REVISED |
| PRELIMINARY ENGINEERING | N/A |
| DESIGN & ENGINEERING (PS&E) | N/A |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 02/08/05 |
| BID OPENING | COMPLETED 03/10/05 |
| TO COUNCIL FOR AWARD | COMPLETED 03/22/05 |
| BEGIN CONSTRUCTION | COMPLETED 05/23/05 |
| END CONSTRUCTION | COMPLETED 07/26/05 ONLY PUNCHLIST ITEMS
REMAIN |
PROJECT NO. CIP 00-412 SEWER REHAB/RECON TARGET AREA 2 TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| |
| PRELIMINARY ENGINEERING - LIMITED LINING ONLY | COMPLETED 07/15/03 |
| DESIGN & ENGINEERING (PS&E) | PARTIAL DESIGN 1/31/05 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 02/08/05 |
| BID OPENING | COMPLETED 03/10/05 |
| TO COUNCIL FOR AWARD | COMPLETED 03/22/05 |
| BEGIN CONSTRUCTION | COMPLETED 05/23/05 |
| END CONSTRUCTION | COMPLETED 07/26/05 ONLY PUNCHLIST
ITEMS REMAIN |
PROJECT NO. CIP 00-413 SEWER IMPROVEMENTS TARGET AREAS 2 THRU 4 TRISTAN MALABANAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| |
| PRELIMINARY ENGINEERING | COMPLETED 07/15/05 |
| DESIGN & ENGINEERING (PS&E) | 2/06 |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 03-418 UPGRADE OF SEWER PUMP STATIONS
| DESCRIPTION | STATUS |
| |
| PRELIMINARY ENGINEERING | COMPLETED 04/28/05 |
| DESIGN & ENGINEERING (PS&E) | 11/05 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 07/26/05 |
| BID OPENING | 11/05 |
| TO COUNCIL FOR AWARD | 12/05 |
| BEGIN CONSTRUCTION | 01/05 |
| END CONSTRUCTION | 03/06 |
PROJECT NO. CIP 04-534 PARK IMPROVEMENTS
| DESCRIPTION | STATUS |
| BOWLING GREEN | E. RODAWAY PARK | FORT LOTS OF FUN |
| PRELIMINARY ENGINEERING | COM 10/7/04 | TBD | COM
01/03/05 |
| DESIGN & ENGINEERING (PS&E) | COM 11/4/04 | TBD |
COM 04/18/05 |
| TO PW COMMISSION FOR REVIEW | N/A | TBD | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | N/A | TBD | N/A |
| BID OPENING | COM. 12/2/04 | TBD | 05/05 |
| TO COUNCIL FOR AWARD | COM. 6/14/05 | TBD | COM 05/10/05 |
| BEGIN CONSTRUCTION | COM. 07/18/05 | TBD | COM. 07/18/05 |
| END CONSTRUCTION | 10/05 | TBD | 10/05 |
PROJECT NO. CIP 04-535 CLARK FIELD IMPROVEMENTS HOMAYOUN BEHBOODI, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION PHASE 2 RICK MORGAN, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES PHASES 3 & 4
| DESCRIPTION | STATUS |
| REVISED |
| PRELIMINARY ENGINEERING | COMPLETED 9/30/04 |
| DESIGN & ENGINEERING (PS&E) | COMPLETED 07/10/05 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 11/05 |
| BID OPENING | 11/05 |
| TO COUNCIL FOR AWARD | 11/05 |
| BEGIN CONSTRUCTION | 12/05 |
| END CONSTRUCTION | 04/06 |
PROJECT NO. CIP 00-630 PIER RENOVATION, PHASE III - TRISTAN MALABANAN, PROJECT
ENGINEER
| DESCRIPTION | STATUS |
| REVISED |
| PRELIMINARY ENGINEERING | COMPLETED 03/08/00 |
| DESIGN & ENGINEERING (PS&E) | COMPLETED 08/29/03 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | COMPLETED 05/27/03 |
| BID OPENING | COMPLETED 07/01/04 |
| TO COUNCIL FOR AWARD | COMPLETED 07/27/04 |
| BEGIN CONSTRUCTION | COMPLETED 09/13/04 |
| END CONSTRUCTION | 10/05 |
PROJECT NO. CIP 99-631 BEACH RESTROOMS REHABILITATION FRANK SENTENO, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
PROJECT NO. CIP 05-633 RE-ROOFING CITY BUILDINGS HOMAYOUN BEHBOODI, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | 09/05 |
| DESIGN & ENGINEERING (PS&E) | 09/05 |
| TO PW COMMISSION FOR REVIEW | N/A |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | 11/05 |
| BID OPENING | 11/05 |
| TO COUNCIL FOR AWARD | 11/05 |
| BEGIN CONSTRUCTION | 11/05 |
| END CONSTRUCTION | 11/05 |
PROJECT NO. CIP 02-634 CITY BUILDINGS EXTERIOR PAINTING HOMAYOUN BEHBOODI, PROJECT ENGINEER
| DESCRIPTION | STATUS |
| PRELIMINARY ENGINEERING | TBD |
| DESIGN & ENGINEERING (PS&E) | TBD |
| TO PW COMMISSION FOR REVIEW | TBD |
| TO COUNCIL FOR APPROVAL TO ADVERTISE | TBD |
| BID OPENING | TBD |
| TO COUNCIL FOR AWARD | TBD |
| BEGIN CONSTRUCTION | TBD |
| END CONSTRUCTION | TBD |
* TBD - TO BE DETERMINED