Project Status Report July 2004

Recommendation:

It is recommended that Council receive and file this report.

Summary:

This report gives the status of capital improvement projects that are either under design or construction. Capital improvement projects not indicated in this report can be found in the department's Monthly Activity Report.

Project Status:

PROJECT NO. CIP 02-106 BEACH DRIVE POST-UNDERGROUNDING STREET IMPROVEMENTS

DESCRIPTIONSTATUS
TBD
PRELIMINARY ENGINEERING
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 02-108 STREET IMPROVEMENTS – 2ND ST. FROM PCH TO THE STRAND; MONTEREY FROM HERONDO TO 4TH ST.

DESCRIPTIONSTATUS
PROJECT ON HOLD
PRELIMINARY ENGINEERINGCOMPLETED 05/07/03
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 04-112 STREET IMPROVEMENTS – SLURRY SEAL AT VARIOUS LOCATIONS

DESCRIPTIONSTATUS
TBD
PRELIMINARY ENGINEERING
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 04-113 STREET IMPROVEMENTS – CONCRETE ROAD RECONSTRUCTION AT VARIOUS LOCATIONS

DESCRIPTIONSTATUS
TBD
PRELIMINARY ENGINEERING
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 04-114 STREET IMPROVEMENTS – SPEED HUMPS ON 24TH PLACE

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGCOMPLETED 7-12-04
DESIGN & ENGINEERING (PS&E)COMPLETED 8-16-04
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENING09/04
TO COUNCIL FOR AWARD09/04
BEGIN CONSTRUCTION10/04
END CONSTRUCTION10/04

PROJECT NO. CIP 04-115 STREET IMPROVEMENTS – 20TH ST. FROM VALLEY DR. TO POWER ST.

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGCOMPLETED 8-16-04
DESIGN & ENGINEERING (PS&E)TBD
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 04-116 STREET IMPROVEMENTS – PIER AVE., HERMOSA AVE. TO PCH

DESCRIPTIONSTATUS
TBD
PRELIMINARY ENGINEERING
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 04-117 STREET IMPROVEMENTS – MANHATTAN AVE. 1ST ST. TO CITY LIMITS

DESCRIPTIONSTATUS
TBD
PRELIMINARY ENGINEERING
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 00-140 11TH PLACE ON-STREET PARKING IMPROVEMENTS

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 12/22/02
UNDERGROUNDING DESIGN BY SCECOMPLETED 02/24/04
PLANS SPECS & ESTIMATESCOMPLETED 06-15-04
TO PW COMMISSION FOR REVIEWCOMPLETED 10/22/03
TO COUNCIL FOR APPROVAL TO ADVERTISE (UNDERGROUNDING)09/04
TO COUNCIL FOR APPROVAL TO ADVERTISE (STREET IMPROVEMENTS)12/04
BID OPENING01/05
TO COUNCIL FOR AWARD02/05
BEGIN CONSTRUCTION03/05
END CONSTRUCTION09/05

PROJECT NO. CIP 99-409* MANHOLE REPAIR/RECONSTRUCTION

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGN/A
DESIGN & ENGINEERING (PS&E)N/A
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISEN/A
BID OPENINGCOMPLETED 06/12/03 WILL BE REBID
TO COUNCIL FOR AWARDTO BE DETERMINED
BEGIN CONSTRUCTIONTO BE DETERMINED
END CONSTRUCTIONTO BE DETERMINED

PROJECT NO. CIP 00-412* SEWER REHAB/RECON TARGET AREA 2

DESCRIPTIONSTATUS
TBD
PRELIMINARY ENGINEERINGCOMPLETED 07-15-03
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 03-418 UPGRADE OF SEWER PUMP STATIONS

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERING09/04
DESIGN & ENGINEERING (PS&E)10/04
TO PW COMMISSION FOR REVIEWTBD
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 04-534 PARK IMPROVEMENTS

DESCRIPTIONSTATUS
TBD
PRELIMINARY ENGINEERING
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 02-612 PUBLIC WORKS YARD RENOVATION

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGBEGUN 7/01/04
DESIGN & ENGINEERING (PS&E)TBD
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

PROJECT NO. CIP 02-626 COMMUNITY CENTER THEATER ADA UPGRADES PHASES 3 & 4

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERING09/04
DESIGN & ENGINEERING (PS&E)12/04
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISE01/05
BID OPENING02/05
TO COUNCIL FOR AWARD02/05
BEGIN CONSTRUCTION03/05
END CONSTRUCTION06/05

PROJECT NO. CIP 00-630 PIER RENOVATION, PHASE III

DESCRIPTIONSTATUS
REVISED
PRELIMINARY ENGINEERINGCOMPLETED 03/08/00
DESIGN & ENGINEERING (PS&E)COMPLETED 08/29/03
TO PW COMMISSION FOR REVIEWN/A
TO COUNCIL FOR APPROVAL TO ADVERTISECOMPLETED 05/27/03
BID OPENINGCOMPLETED 07/01/04
TO COUNCIL FOR AWARDCOMPLETED 07/27/04
BEGIN CONSTRUCTION9/13/04
END CONSTRUCTION08/05

PROJECT NO. CIP 02-634 CITY BUILDINGS – EXTERIOR PAINTING

DESCRIPTIONSTATUS
PRELIMINARY ENGINEERINGTBD
DESIGN & ENGINEERING (PS&E)
TO PW COMMISSION FOR REVIEW
TO COUNCIL FOR APPROVAL TO ADVERTISE
BID OPENING
TO COUNCIL FOR AWARD
BEGIN CONSTRUCTION
END CONSTRUCTION

* TBD - TO BE DETERMINED